Topics

A

Search

Kugira: The Floating Factory That Builds Docks In Record Time

Expanding the size and operating capacity of ports in record time with the minimal environmental impact is a true engineering challenge. One of the most advanced options meeting this challenge are floating factories or floating docks, like Kugira (from Acciona), which builds the gigantic blocks of concrete (caissons) that comprise the berthing lines in ports.

Posted on 07.26.2018
Kugira is the floating dock of large dimensions of the company Acciona. [Image: Acciona]
Adapting infrastructures to the new market demands is one of the most complex engineering jobs around, while it also entails a host of difficulties, such as the ever-changing conditions of the sea, interference with port activity and the environmental effects of building wharves and docks. To minimise these problems, floating docks were created, structures based on two main principles: modularity and in-situ construction. These movable factories, called caisson-building docks, manufacture concrete caissons which are later transported to their final location (berthing line or dock), where they are installed. The caisson-building docks are located near the dock that is being built to make it easier to transport the caissons.

A ‘whale’ contributing to port construction

One of the largest caisson-building docks in the world is the Kugira (‘whale’ in Japanese). This herculean machine from ACCIONA measures the equivalent of an 18-floor building (56 metres tall, 74 metres long and 49 metres wide). A team of between 140 and 200 high specialised professionals work on the Kugira around the clock seven days a week, and it can manufacture concrete caissons weighing up to 24,000 tonnes. This means that it can create a seawall or a berthing dock 200 metres long from scratch in just one month. Despite its colossal size, the way this engineering whale works is based on simple principles. It begins by building the base (shoe) on which the caisson walls will be erected. The steel bar frame of this shoe is made on a flat floating surface (pontoons) on which the frame supporting the concrete is woven. To complete the assembly, it is placed on the floating dock and the concrete is poured. Once the concrete on the shoe is finished, the scaffolding is lowered, which acts as the mould for the walls, and the concrete is pumped in through three boom pumps fed by lorries which transport the concrete from the place where it is mixed. The formwork is slid using a system similar to the one used in bridge hoisting, which allows the walls to be filled with concrete without interruptions. This makes the sliding more precise, on the order of millimetres. Furthermore, the Kugira’s floating capacity allows it to dry-build a caisson measuring 18,000 tonnes.

Adapting infrastructures to the new market demands entails a host of difficulties, such as the ever-changing conditions of the sea, interference with port activity and the environmental effects of building wharves and docks.

Once a caisson is completed, it is launched by being partially sunk until the caisson can float, and then it is taken by tugboats to the place where it will be placed over the platform on the sea floor, where tonnes of material has previously been laid to create a uniform base. Once it is in its exact position, the caisson is secured in place by filling the cells with water, and later they are filled with sand to make them completely stable. Although this procedure may sound cumbersome, it does not interfere with port activity.

Advantages of caisson-building docks

The most obvious advantages are the speed and the reduction in the consumption of material. This means not only time- and money-savings but also a significant decrease in the amount of quarry materials required compared to other building techniques.
  • It is a highly versatile methodology since it adapts to the different ways the dock is used. “One good example is Port of Barcelona”, says Domingo González, Construction Director of the Business Unit Specialised in Ports and Hydraulic Works of ACCIONA Construction. “The extension of a dock for a cruise terminal was built, but if it has to be used for general cargo in the future, with everything this means in terms of larger overloads on the dock, the caisson will allow its use to be changed without having to change the infrastructure”. With a solution using piles, this would not be possible.
  • Furthermore, since it works in the sea, the Kugira can be installed in a location where it does not interfere with port activity, so its economic activity is not harmed during expansion. Tugboats can take this colossal factory wherever it is needed.
  • It can build longer caissons. “In Barcelona, the caissons are 40.3 metres, but we could have reached up to 66 metres. The largest caissons allow a large dock to be built in a single operation. In the case of Port of Barcelona, we manufactured a caisson every 7 days, and after a month we had 170 metres of dock. We finished the caissons in 49 days”, says Domingo González.
  • Less quarry material is used than in a solution using piles because only the platform that serves as the base of the caisson is needed.
  • Finally, “the caisson system allows for greater flexibility and provides better durability than what other structures can”, states Domingo González. They are reinforced concrete caissons, and while metal solutions usually require excess thicknesses or sacrificial anodes because they corrode, there are caissons from the 1970s which are still in perfect condition today.

The most recent work of the Kugira has been the enlargement of the Adossat dock in the Port of Barcelona, necessary due to the constant increase in the activity of the port.

Expansion of the Adossat wharf

The most recent project by this naval colossus was the enlargement of the Adossat wharf in Port of Barcelona, which was essential due to the steady increase in port activity. The objective was to build an additional berthing line 290 metres long and 16 metres deep, which would include a ro-ro infrastructure (for ferry operators and roll on-roll off cargo) which could allow two ships to embark and disembark simultaneously. The joint venture of ACCIONA Construction and Copcisa was awarded the project. The structural typology chosen consisted in manufacturing seven reinforced concrete caissons, which at this time have already been sunk to their definitive location. Each of these caissons weighs more than 8,000 tonnes and measures more than 40 metres long. To manufacture it, the Kugira had to be anchored in a shallow area. This meant that first, the caisson had to be built dry and secondly a pit 20 metres deep had to be dug near the Kugira to sink it. “The Kugira precisely allows us to do this”, states the director of Construction of Ports and Hydraulic works of ACCIONA Construction, “to adapt to the size of each project”. Furthermore, “the project in Port of Barcelona had a special particularity”, he continues, “since we did not have a berth for the Kugira, so we did not interfere in port operations. As a result, we had to locate it in a dock on a bank just 7 metres deep. Usually, the caisson-building dock needs 13 metres to operate, but thanks to its incredible ability to float, we were able to carry out the entire process almost dry; with just 5 metres of depth, we were able to manufacture caissons weighing 8,000 tonnes”. To set it afloat, a trench outside the execution area had to be dredged. The Kugira was moved there and it sunk and released the caisson and was put back in position. “This is the first time the Kugira carried out this type of operation in which almost the entire caisson was built dry”, claims Domingo González. “This was only possible due to the enormous floating capacity of this caisson-building dock”, he concludes. And in this effective and almost surgical way, which is quick and minimally intrusive, the Kugira managed to expand the Adossat wharf in Port of Barcelona. The end result will be unveiled late this year when construction is completed.